Milestones

  • Community Engagement

    August 2021

     

    -

     

    September 2021

    Share proposals with local residents and gather their feedback on the proposals.
  • Refine proposals

    September 2021

     

    -

     

    October 2021

    Refine proposals based upon feedback from the community engagement.
  • Final Masterplan

    Gather thoughts relating to the refined masterplan proposals. Begin a process of incorporating final community feedback into the masterplan designs
  • Planning Application

    October 2022

     

    -

     

    October 2022

    Submission of planning application
  • Planning Application Approved

    April 2023

     

    -

     

    Complete

  • Site preparation

    March 2024

     

    -

     

    TBC

  • Construction of new homes and delivery of wider improvements

    summer 2024

     

    -

     

    summer 2026

  • Homes Completed

    summer 2026

     

    -

     